Project Schedule

Outreach

April 2021
  • Initial Landowner Notification for GPS permissions (100% obtained)
October 2021
  • Initial communication to permitting agencies of expansion plan and addition to existing infrastructure
December 2021
  • Initial communication to landowners and Project stakeholders
January 2022
  • Additional landowner information and notification
  • Project filing for certificate of Public Convenience and Necessity
March 2022
  • Mailings to stakeholders and media outreach
  • Greene County and Wetzel County open houses
  • Monroe County Information Session
July 2022
  • Equitrans Midstream releases Environmental Justice Policy

Construction Commencement

Summer 2023
  • Corona Compressor Station
  • Plasma Compressor Station
  • H-326 Pipeline
  • H-329 Pipeline
  • H-330 Pipeline
Summer 2024 (Targeted)
  • Cygrymus Compressor Station
Winter 2025 (Targeted)
  • H-327 Pipeline
  • H-328 Pipeline

Regulatory Approval Timeline