April 2021
- Initial Landowner Notification for GPS permissions (100% obtained)
October 2021
- Initial communication to permitting agencies of expansion plan and addition to existing infrastructure
December 2021
- Initial communication to landowners and Project stakeholders
January 2022
- Additional landowner information and notification
- Project filing for certificate of Public Convenience and Necessity
March 2022
- Mailings to stakeholders and media outreach
- Greene County and Wetzel County open houses
- Monroe County Information Session
July 2022
- Equitrans Midstream releases Environmental Justice Policy
Construction Commencement
Summer 2023
- Corona Compressor Station
- Plasma Compressor Station
- H-326 Pipeline
- H-329 Pipeline
- H-330 Pipeline
Summer 2024 (Targeted)
- Cygrymus Compressor Station
Winter 2025 (Targeted)
- H-327 Pipeline
- H-328 Pipeline